
CLIENT:
YEAR:
Major works included:
- Design of temporary works and the installation of a clay cofferdam and dewatering to bund off and control the canal. 
- Demolition of the existing pump station componentry to allow for new concrete and metal work. 
- Excavation and subgrade improvements including 14m timber piles with concrete pile cap foundations. 
- The new pump station inlet comprised of precast concrete walls placed on the concrete pile cap foundations. The panels were tied in with a concrete floor and in-situ stitch joints to the existing structure. 
- The design and construct for a precast hollowcore deck which included an in-situ concrete topping slab. These items required a PS1 and PS3. 
- The removal and replacement of all mechanical componentry with the replacement of large sluice gates. 
- Site reinstatement which included retaining walls, timber steps and fences, metal access tracks and grassing. 
This project was completed in May 2018.
.png)


















